Dear Brothers,
We are happy to provide you with a brief progress update on the Warwick Project and explain how you can assist with a major adjustment recently approved in our construction schedule. Thus far, almost 27,000 have been able to have a share in the work at Warwick. Many of you are among them and you have personally seen Jehovah’s spirit in operation both at the project and with your personal circumstances enabling you to come and work. Preparations are underway to obtain certificates of occupancy for two of the four residence buildings which will soon be occupied by hundreds of volunteers assisting on the project. Much work is also underway to complete the large Maintenance Building and Offices/Services Building.
In order to make the best use of dedicated funds and assist with other theocratic directives, the Governing Body recently adjusted the project completion date from December 31, 2016 to September 1, 2016. Since this has reduced the project timeline by four months, various construction schedules are being updated, which directly affects when certain trades are needed.
While we will continue to need volunteers to complete the project through next summer, it appears the bulk of the work will take place during the time frames below. Thus, if you have not yet had the opportunity to work at Warwick or had hoped to return again before project completion, now is the time to make yourself available. We have a need for additional volunteers beginning in November and December in the marked trades below (*) and will continue to need them until the time frame noted. This does not mean all CG work will end at that time, but rather we expect the bulk of the CG work for those trades to wind down. Due to rooming constraints we are only able to invite those with advanced skills in their trade. Although many wish to volunteer with their mate, this is no longer possible in most cases.
TRADE Starting Ending Electrical 11/12/2015 Early April 2016 Interiors (Paint) 02/01/2016 July 2016 Interiors (Tile) 11/30/2015 June 2016 Plumbing (Plumber) * 11/12/2015 Late February 2016 Plumbing (Spr Fitter) * 11/12/2015 Late January 2016 Walls & Ceilings (Drop Ceiling) 12/21/2015 Late July 2016 W&C (DW Finish) * 11/12/2015 Early April 2016 W&C (DW Hanging) * 11/12/2015 Mid-March 2016 W&C (Framer) * 11/12/2015 February 2016 To indicate your availability:
If previously approved by your Construction Group – please contact your Construction Group by e-mail with your availability. (See attachment)
If you previously submitted a Temporary Volunteer application, you can alert the Warwick Volunteer desk of your availability at [email protected].Your brothers,